Phases of Systems Development Life Cycle (SDLC)
- System analysis
- System design
- System implementation
- System testing
- System conversion
- System maintenance
Overview: Tasks involved in each phase
| System analysis | • System analysts collect users requirements and write system requirement specifications |
| System design | • System analysts design user interfaces and draw flowcharts for the system |
| System implementation | • Programmers write the source codes of the system |
| System testing | • Unit testing, system testing and users acceptance testing are performed |
| System conversion | |
| System maintenance |
System Analysis
The following should be done in the system analysis:
- Collecting users’ requirements [DSE 2015 P2D Q2(b)(i), DSE 2018 P2D Q2(c)]
- Conducting feasibility study
Collecting users’ requirements
A system analyst needs to collect the following information:
- The function of the system
- The users of the system
- Major dataflow of the system
- Existing hardware and software of the system
- Process time and capacity
There are different ways to collect user requirements [DSE 2015 P2D Q2(b)(i), DSE 2018 P2D Q2(c)]
- Interviews
- Questionnaires
- Observation
- Documentation reviews (e.g., documentation of the existing system)
Feasibility study
- It is used to assess the effectiveness of various solutions
Three are three aspects of the feasibility study:
| Technical feasibility | • Evaluate whether the objectives can be achieved using the current level of technologies |
| Operational feasibility | • Evaluate the effects of the system on employees and customers |
| Economic feasibility | • Evaluate using cost and benefit analysis • Estimating the costs and the benefits of the system • If marginal benefit ≥ marginal cost then implement, else not implement |
System Requirement Specifications (SRS)
Requirements include:
- Business requirement
- Functional requirement
- Non-functional requirement
| Functions | |
| Business requirement | • Requirements that company needs / functions that the company expected |
| Functional requirement | • What the system must do to fulfill business requirements • Emphasizes functions provided by the system e.g., input / output methods |
| Non-functional requirement | • About other aspects of the system apart from the functions • e.g., system performance, costs, reliability, security, portability |
System Design
Components of a computer-based system
- Hardware platform
- Software
- Inputs
- Outputs
- User interface
- Data (e.g., Database, Data processing, Data control, Data security)
- System security
Types of user interface
- Command Line Interface (CLI)
- Graphical User Interface (GUI)
System design tools
- System flowchart
- Structure chart
- Data flow diagram (DFD)
- Data dictionary
Data Flow diagram (DFD) [DSE 2013 P2D Q3(c), DSE 2015 P2D Q4(a)]
- Showing the main requirements of a system
- Showing the process, information/data flow in, and out of the system
- Showing what data will be stored
Gantt Chart [DSE 2019 P2D Q3(a)(iii), DSE 2021 P2D Q2(d)]
Usage
- Project management
Clarifies the project schedule by illustrating multiple tasks and timelines into a single document[DSE 2019 P2D Q3(a)(iii)]
→ helping project managers to make a realistic assessment of the progress / the completion of time
Showing the dependencies between various tasks and concurrent activities/tasks that are going [DSE 2019 P2D Q3(a)(iii)]
Supports critical path analysis [DSE 2019 P2D Q3(a)(iii)]
What is critical path?
- A critical path is a sequence of tasks in a project that must be completed in order to ensure that the project is finished on time
System Testing
| Function | Done by who? | |
| Unit test | • To ensure that a particular module performs its function as defined in specification / does not contain error | • Implemented by developers who write the modules |
| System test | • Implemented by developers who write the modules | • Done by developers |
| Acceptance test | • To ensure the system meet the company’s users’ requirements • Test the system with authentic data | • Done by ultimate users to test the system with authentic data |
Order of system testing (from the first to the end): [DSE 2017 P2D Q3(c)]
Unit test → System test → Acceptance test
Supplementary notes: There are three types of system test
Volume test
- Functions
To determine whether the system can handle the volume of activities that occur during the peak of processing demands
Storage test
- Functions
To test whether the storage capacity of a system can store all transaction data
Performance time test
- Functions
To test the length of time used by the system to process data
System Conversion
| Direct cutover conversion | Parallel conversion | Phased conversion | Pilot conversion | |
| Characteristics | [DSE 2018 P2D Q2(d)] • The original system is instantly changed to the new system on a given date | [DSE 2018 P2D Q2(d)] • Both systems run for some periods at the same time | • Different modules of the new system are replaced in different phases | • The new system is installed in specific places (pilots, a subset of an organization) |
| When this conversion should be implemented? | • System cannot be run in parallel • System is not critical • Insufficient resources | • The system that cannot tolerate failure / risks made by conversion • Important resources for the system are available | • Suitable for a large and complex system which is difficult to be implemented in one single phase | • Higher risks of the new system and its impacts on the organization are hard to predict |
| Advantages | [DSE 2012 P2D Q2(c)(ii), DSE 2018 P2D Q2(d), DSE 2020 P2D Q4(c)] • Lowest cost of conversion (money, manpower, time) within all conversion • No need to manage two systems at the same time | [DSE 2019 P2D Q3(a)(iv)] • The risks of conversion is low [The old system can act as a backup, if the new system cannot be operated, operation will not be disrupted] • Compare the results / outputs of two systems → easier to find out bugs / errors in the new system | • As the conversion is done in parts, time is available for adjustment • Lower risks of conversion → impacts of the. failure of new phase will be limited | [DSE 2020 P2D Q4(c), DSE 2022 P2D Q3(f)] • Minimizes the impacts on changes → Errors are contained to the first implemented locations only, with limited harmful effects on other places → Reducing the risks of conversion • Other places can learn from the experience from pilots, especially in terms of operations |
| Disadvantages | [DSE 2012 P2D Q2(c)(i)] • If there is any problem in the new system → disrupt the operation → the entire system will be affected → higher risks | • Parallel run is not feasible under some scenarios • Extra resources are needed for running two systems at the same time | • If the components of a system is very dependent/integrated, implementing phased conversion will be difficult due to difficulties in dividing into different phases → Increasing the complexity of conversion | • Even if the system is run successfully in pilots, it does not mean that other places can be run successfully too |
Factors affecting the choice of conversion
- Risks
- Costs
System maintenance
Why is system maintenance needed? [DSE 2020 P2D Q4(d)]
- Adding / improving more functions/features
- Fixing program bugs
- Improving security
- Improving efficiency
System Documentation
- System documentation should be done throughout different stages
System documentation [DSE 2015 P2D Q2(b)(ii), DSE 2022 P2D Q4(d)(ii)]
| Audience | Function | |
|---|---|---|
| User manual | Users | Teach users how to use the system |
| Technical documentation | Developers | Enabling them to understand the system and do the maintenance |
Alternative Approaches in System Development
| When to use? | Advantages | Disadvantages | |
| Waterfall model | • User requirements are fixed / completed → waterfall model is more systematic | More systematic (Need to complete the previous stage before going to the next stage) | • Longer development time • Only applicable to projects with clear and frozen requirements |
| Prototype Approach | • Creating a prototype first for a complex system → allowing feedback and insight to be incorporated into the future system | Reducing development time | • The prototype may not able to accurately reflect the performance of the actual system |
| RAD (Rapid application development) | • Design and implementation processes are done in an interleave, iterative manner (alternatively) • User requirements are not completed / changing → more flexible | Reducing the development time | [DSE 2016 P2D Q1(a)(iv)] • Requires sufficient resources (e.g. highly skilled developers) to create the right number of RAD teams • If the system cannot be properly modularized, building components for RAD will be problematic • Requires user involvement during implementation • Lower program re-usability |
Related jobs of system development
[DSE Practice Paper P2D Q4(e), DSE 2019 P2D Q3(a)]
- Project manager
- System analyst
- Programmer
- Database administrator
- Computer operator
- Technical support staff
| Main duties | |
| Project managers | • Assign resources and roles to members of the development team • Set essential milestones of the development plan |
| System analyst | • Communicate with users e.g., collect user requirements • Write user requirement specifications • Doing system design |
| Programmer | • Code the program • Carry out testing |